The first column contains the list of Activities and Milestones for the Implementation Plan and can’t be moved around.
As of the Orion Release (v.1.41) The width of individual columns in the Activity Table by can be adjusted by simply dragging to fit more text within each column. Once adjusted, the table remembers the new layout, ensuring the same column widths are displayed when users navigate back to the Activity Table.
Status colour Green title ORION (1.41) Each Activity record is hyperlinked and clicking on the hyperlink will open the Activity record in a new tab whereas double-clicking in the Activity row will bring up the Activity Edit pop-up.
Info |
---|
Activity Table in Experience Sites: The Activity records won’t be hyperlinked. Instead, users will be able to us the Activity Edit pop-up to modify Activity records. . Instead, users will be able to us the Activity Edit pop-up to modify Activity records. |
The Activity Table will revert to its default column widths upon refresh or when a new activity is added or edited.
Status | ||||
---|---|---|---|---|
|
The following dates can be tracked for Tasks.
Planned Start Date
Planned End Date
Actual Start Date
Actual End Date
Due Date can be tracked for Milestones.
...
If multiple Activities have the same value in “Earliest Start Date” then those Activities will be sorted in order of alphabetically ascending Name value.
...
Name value.
...
The downloaded Implementation Plan Excel sorts Activities based on the ‘Earliest Start Date’, aligning with the default sorting order of the Activity Table.
Status | ||||
---|---|---|---|---|
|
Filter Activities
Filter Activities to display or modify specific parts of the project plan.
...
When you drag and drop activities to easily reschedule them, the Actual Start Date and Actual End Date associated with the Activity will be updated to reflect new values.the Activity will be updated to reflect new values.
When you drag and drop activities to easily reschedule them, the Activity table will maintain its scroll position, sort order, and column width.
Status | ||||
---|---|---|---|---|
|
Track Percent Completion
Mark progress for an Activity by filling in the timeline bar to indicate the percent completion.
...
Info |
---|
Note: An Implementation Plan can also be submitted and locked as a part of the “Submit and Lock” wizard. |
Note |
---|
System Admin Note: When the “Override Locked Implementation Plan ” custom permission is assigned to a user they can make edits to the Activities/Milestones even if activities LWC has been locked. Read more here. |
...