Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Info

Trying to add Activities or Milestones to your Project Plan? Make sure you created an Implementation Plan first before adding Activities.

...

Activities & Milestones in Amp Impact

Once you created the Implementation Plan, you can start adding Activities to track project progress. An Activity is a set task performed under an Implementation Plan. There are two types of activities that can be added to an implementation plan: tasks and milestones. While the Implementation Plan record creates the structure of the project plan, Tasks and Milestones track the granular tasks that need to be done through the life of the project.

...

Features

Status
colourRed
titleAura Component

Status
colourPurple
titleLightning Web Component

View planned and actual timeline of Activities

(tick)

(tick)

View Activities by Year, Month and Week

(tick)

(tick)

Create Child Activities

(tick)

(tick)

View Activities from multiple Implementation Plans

(error)

(tick)

Add Milestone Activities

(error)

(tick)

Activity Dependencies

(error)

(tick)

Drag and Drop Rescheduling of Activities

(error)

(tick)

Track Percent Completion of Activities

(error)

(tick)

Display Critical Path

(error)

(tick)

...

Add/Edit/Remove Activities in an Implementation Plan
Status
colourPurple
titleLightning Web Component

Add a Task Activity to the Activity Table
Status
colourPurple
titleLightning Web Component

  1. Navigate to the “Activities” or “Project Plan” section of your Project and select an Implementation Plan from the picklist. Click on “Add New Activity” and then click on the “Create Task” option to add a Task
    Activity to an implementation plan.

  2. Fill out the details for the Activity record, including the “Activity Name”, “Type”, “Description”, “Activity Information”, “Parent Activity”, “Location” and “Status”.

  3. Filling out the “Parent Activity” field allows you to build a hierarchy of Activities to track related Activities:

    1. All the sub-activities appear beneath the Parent Activity within the Activity Table. A chevron associated with the Parent Activity enables you to hide and display and hide all the sub-activities. To remove parent-child relationships, navigate to the Edit Activity popup for the child Activity and remove the parent relationship.

  4. The date values in the “Planned Start Date” and “Planned End Date” as well as the “Actual Start Date” and “Actual End Date” fields determine how the timeline bars appear on the Activity Gantt Chart: 

    1. If both Start and End Dates are filled out, a horizontal timeline bar will appear on the Gantt Chart;

    2. If either the Start or End Date is filled out then a tick representing the date will appear on the Gantt Chart; 

    3. The Baseline bar that showcases the duration between “Planned Start Date” and “Planned End Date” will only appear if you click on the “Display Baseline” button. Refer to the Edit Activity section for more details.

  5. To track any stakeholders who are responsible to complete or contribute to an Activity, fill out the “Contact” field. Organizations often rename this field to something like “Responsible” but this relationship essentially tracks people related to Activities. Note that the relevant record (e.g. a Contact record) must be created first before an Activity can be related to that record.

  6. Activities can be related to multiple Project Indicators and Framework Objectives. This allows organizations to track their progress toward their goals and helps them track how the Project Activities will ultimately contribute to their impact.

    1. Only Framework Objectives and Project Indicators associated with the current Project are displayed in the dropdown list of options.

    2. Framework Objective options are limited to the Framework related to your Implementation Plan record. However, if no Framework is related to the Implementation Plan level, all the Objectives in your system will be available.

...

7. When you click on the Save button, an Activity will be created and a success message will be displayed.

...

Add a Milestone Activity to the Activity Table
Status
colourPurple
titleLightning Web Component

  1. Click on “Add New Activity” and then click on the “Create Milestone” option to add a Milestone
    Activity to an implementation plan.<Add Image>

  2. Fill in the and Name field as it is required for the milestone activity to save successfully. Optionally, you can also:

    1. Add an ‘Activity Description’

    2. Link a ‘Parent Activity’ based on the information mentioned in the previous section

    3. Select a ‘Status’ for the Activity - Open/Closed

    4. Link a ‘Disbursement’ to the Activity

    5. Specify a ‘Due Date’ for the Milestone Activity

...

Info

System Administrator Note: The fields in the popup are defined and can be customized using the
CREATE_EDIT_MILESTONE_POPUP field set on the Activity__c object.

Edit an Activity in an Implementation Plan
Status
colourPurple
titleLightning Web Component

To modify an Activity (for example, update its Status or mark the Actual End Date), simply double-click on the Activity from the Activity Table. A pop-up will open up where fields can be modified.

...

Info

The color of the Planned timeline bar is Grey by default and the Actual timeline bar is Blue by default.

Remove an Activity from an Implementation Plan
Status
colourPurple
titleLightning Web Component

To remove an Activity from an Implementation Plan (and delete the record), double-click on the relevant Activity on the Activity Table to bring up the pop-up to edit the Activity.

Click delete and confirm the deletion of the Activity. After you confirm the removal of an Activity, the Activity is deleted and no longer displayed in the Activity Table. A success message displays to confirm the Activity’s deletion.

...

Navigate the Activities Table
Status
colourPurple
titleLightning Web Component

Now that your Activity Tasks and Milestones are created, you can view and manage them in the Activity Table.

Activity Table
Status
colourPurple
titleLightning Web Component

Below is an example of an Activity Table with Parent and Child Tasks, a Milestone Activity (indicated by the diamond), and blue bars indicating the Start and End Dates of the Activities.

...

  1. Earliest start date: The start date associated with an Activity that happens first - the planned date or the actual date. For a Milestone Activity, it will be the due date.

  2. Duration: The number of days tracked for an Activity based on the actual start and end dates.  

View by Year, Month, Week 
Status
colourPurple
titleLightning Web Component

The “View By” toggle feature offers flexibility in terms of how you can view the Activity Gantt Chart. This toggle can be used to view Activities in Year, Month, and Week views. By default, the Activity Table displays the Year view.

...

Activity Info Pop-Up
Status
colourPurple
titleLightning Web Component

Hovering over any of the Activities in the Activity Table brings up an information pop-up with details about that Activity.

...

Info

For both the Planned and Actual fields, if the Start Date is empty and the End Date has a value or vice-versa then both the Start Date and End Date will be populated with the non-null value on the info pop-up. However, the Activity record will be created so that the empty field will have no value. 

View Activities across Multiple Implementation Plans
Status
colourPurple
titleLightning Web Component

For some projects it makes sense to view the Activities and Milestones for multiple Implementation Plans. Simply select the relevant Implementation Plans from the multi-select dropdown picklist. All the Activities from the Implementation Plans that you have selected displays in the Activity Table. 

...

Toggle Baseline On/Off
Status
colourPurple
titleLightning Web Component

The “Baseline” refers to the grey bars that indicate the Planned Start and End Dates. Milestone Activities do not have baseline values associated with them.

...

  • Hide Baseline: This hides the timeline bars associated with Planned Start Date and End Date for all Activities to only display the Actual Dates.

...

Toggle Critical Path On/Off
Status
colourPurple
titleLightning Web Component

Critical Path is an Activity or a set of Activities within an Implementation Plan that must start and finish on time to ensure that the project ends on schedule. If the Critical Path gets delayed the entire project gets delayed. Critical Path also determines the shortest time a project can take to complete. 

...

  • Display Critical Path: Click on the “Display Critical Path” button to highlight in the Critical Path Activities in the Activities Gantt chart.

  • Hide Critical Path: Click on the “Hide Critical Path” button to remove the highlighting of the Critical Path Activities.

Refresh when Updates on Relevant Pages affect Activities
Status
colourPurple
titleLightning Web Component

Changes (add, edit, delete) to records that are related to Activities trigger a refresh banner to prompt the logged in user to refresh the page to see the latest data. The page can be refreshed to display the latest updates by clicking on the ‘refresh’ button located to the right of the ‘Display Critical Path’ button.

...

  1. Add, edit, or delete operations on Indicators

  2. Add, edit, or delete operations on Frameworks

Sort the Activity Table
Status
colourPurple
titleLightning Web Component

Users can click on any of the columns to sort the list of Activities. By default, the Activity Table is sorted in ascending order for Earliest_Start_Date__c so that Activities with earlier start dates (either planned or actual) are displayed above Activities with later start dates.

...

If multiple Activities have the same value in Earliest_Start_Date__c, then those Activities will be sorted in order of alphabetically ascending Name value.

...

Filter Activities
Status
colourPurple
titleLightning Web Component

Filter Activities to display or modify specific parts of the project plan.

...

Info

The System Administrator has the ability add additional fields in the search filter, so reach out if you require specific field values.

...

Managing Activities through the Project
Status
colourPurple
titleLightning Web Component

Once your Activities and Milestones are set up, project teams typically have to manage Projects on an ongoing basis, updating Activity dates, progress, or other changes.

This section calls out the Activity elements that are typically updated as the Project progresses.

Activity Duration
Status
colourPurple
titleLightning Web Component

The duration of an Activity is the number of days between the Actual Start Date and Actual End Date. You can also view the duration of an Activity as the length of the Activity timeline bar on the Gantt Chart. 

For Activities that start and end on the same date, the duration value equals to 1 day. If an Activity has a Start Date but no End Date, the duration value equals to 0. 

...

Activity Dependencies
Status
colourPurple
titleLightning Web Component

Project managers typically need to track Activity dependencies through their projects. Amp Impact allows organizations to track four types of dependencies:

  1. Start to start: This type of dependency between two activities indicates that one Activity can only start after the other one starts.

  2. Start to finish: This type of dependency between two activities indicates that one Activity can only finish after the other one starts.

  3. Finish to start: This type of dependency between two activities indicates that one Activity can only start after the other one finishes.

  4. Finish to finish: This type of dependency between two activities indicates that one Activity can only finish after the other one finishes.

Add a Dependency

To create a dependency between two Activities in the Gantt chart, click on the leading Activity and drag the dependency arrow to the following Activity.

...

Delete a Dependency

Delete a dependency in the Gantt chart by double-clicking on the relevant dependency link and clicking on the “Delete” button in the confirmation popup.

...

Info

Dependency type cannot be updated once a dependency is created. Instead, delete the Activity dependency and create a new dependency to represent a different dependency type.

Drag and Drop Rescheduling
Status
colourPurple
titleLightning Web Component

Click on the Activity’s timeline bar within the Gantt Chart and drag horizontally drag it to a new place in the Implementation Plan’s timeline to reschedule. You can only drag and drop activities according to the vertical lines available on the Gantt Chart. Therefore, in the View by Year filter, it would only be possible to reschedule to the first of any given month. If you want more granular control over rescheduling you would have to toggle to View by Month or View by Week mode. 

...

When you drag and drop activities to easily reschedule them, the Actual Start Date and Actual End Date associated with the Activity will be updated to reflect new values.

Track Percent Completion
Status
colourPurple
titleLightning Web Component

Mark progress for an Activity by filling in the timeline bar to indicate the percent completion.

...