As with some of the other features, Amp Impact comes with two options for displaying and managing Activities & Milestones in the Activities Table: Aura and Lightning Web Components. Depending on which option your organization uses, the interface will be slightly different. In this guide, we only focus on Lightning Web Components. Check with your System Administrator if you’re unsure which option you are using, or need additional guidance.

Features

Status
colourRed
titleAura Component

Status
colourPurple
titleLightning Web Component

View planned and actual timeline of Activities

(tick)

(tick)

View Activities by Year, Month and Week

(tick)

(tick)

Create Child Activities

(tick)

(tick)

View Activities from multiple Implementation Plans

(error)

(tick)

Add Milestone Activities

(error)

(tick)

Activity Dependencies

(error)

(tick)

Drag and Drop Rescheduling of Activities

(error)

(tick)

Track Percent Completion of Activities

(error)

(tick)

Display Critical Path

(error)

(tick)

...

Info

The color of the Planned timeline bar is Grey by default and the Actual timeline bar is Blue by default.

Info

To learn about how to customize colors of Activities Lightning Web Component to suit your organization’s branding, refer to the Amp Impact Installation Guide

Remove an Activity from an Implementation Plan
Status
colourPurple
titleLightning Web Component

...

  1. You can define the Percent Complete field for an Activity directly from the Gantt chart by hovering on top of an Activity, clicking, and dragging the slider that appears to the appropriate value

  2. You can also add the Percent Complete field to the Edit/Create Activity  pop-ups and set the value while creating or editing an Activity

  3. The Percent Complete value is displayed on an Activity within the Gantt chart in the form of a progress text that appears on the timeline bar. Additionally, if there is a Percent Complete value, a portion of the timeline bar would have a darker colour color as opposed to the default colourcolor

  4. By default, all activities have a Percent Complete value of 0

...